Building ContractsA building contract, like all contracts, should ideally be in writing in order to reduce the potential for disagreement about what was agreed by the parties. However for a variety of reasons contracts are not always in writing.Parts of the contract may be in writing – there may be a specification and an estimate - but important terms, such as completion date and terms of payment, may have been agreed verbally, or may not have been expressly agreed at all, and it may fall to the court, after hearing argument from each side’s barrister to decide what terms should be implied by law. As well as terms which might be implied by the particular circumstances, there can be presumptions which apply. For example where a long and costly piece of work is to be carried out there is a presumption that the contractor is entitled to interim payments as work proceeds even where the Housing Grants, Construction and Regeneration Act 1996 (which gives a statutory right to interim payments in certain circumstances) does not apply. Breach of ContractIf the contractor is guilty of a breach of the contract which is so
serious that it amounts to a “repudiatory” breach then the
employer can bring the contract to an end and claim compensation for
loss. Such compensation might include the extra cost of completing the
work (over and above the price which the employer had expected to pay
under the original contract) and possibly the knock-on effects of delay
(such as loss of rental income if the property under construction is to
be let). Likewise if the employer is guilty of repudiatory breach, the contractor can bring the contract to an end and claim the amount due for the partly completed work plus the profit element lost on the uncompleted portion. If however the employer terminates the contract when the contractor is not in repudiatory breach, that means that he employer is, because of the wrongful termination, itself in repudiatory breach. Similarly if the contractor terminates when the employer was not in repudiatory breach, that means that the contractor is in repudiatory breach. It is important, therefore, to take legal advice before terminating, as a termination which a court later decides is unjustified can be costly. The fact that the other party is in breach of contract does not necessarily justify termination – it depends on how serious the breach is. DamagesThe party claiming compensation has to show that their loss was caused by the other party’s breach of contract and the “innocent” party is expected to take reasonable steps to minimise their loss. One issue which may arise if the employer has justifiably terminated the contract is whether the employer should allow the contractor access to rectify defects. This may well be less expensive than a new contractor to rectifying defects but on the other hand the employer may have no confidence in the old contractor doing this work. Ultimately the court may have to decide whether a refusal of access is reasonable.This page was lasted updated in October 2010. Disclaimer |
